A homeowner sought to convert the basement of their two-story, double-fronted Victorian home, built around 1860, into a functional living space. The brief was to create a playroom, guest bedroom, and a wet room within the existing basement, which consisted of two rooms and a wide hallway. The project involved addressing structural, spatial, and moisture control challenges to transform the underutilised space into a comfortable and compliant living area.

The Challenge

Victorian properties often present unique challenges for modern basement conversions due to:

  • Limited headroom caused by the original shallow floor level.
  • Soft, porous brickwork prone to water ingress.
  • Variable foundation depths, complicating excavation and levelling.
  • The need for effective moisture control to achieve a dry, liveable space suitable for modern use.

The requirement to meet BS8102 Grade 3 environmental standards for habitable basements.

The Solution

To address these challenges, a comprehensive approach was implemented:

  1. Excavation and Floor Levelling:
    • The basement floor was excavated as deeply as the existing foundations allowed to maximize headroom.
    • Due to varying foundation depths between rooms, a stepped floor level was designed and constructed.
    • A new concrete slab was laid throughout for a solid, level base.
  2. Waterproofing and Drainage System:
    • The Oldroyd Xv Clear Cavity Drainage Membrane System was selected over traditional cementitious or epoxy waterproofing. This membrane:
      • Redirects water to a sump and pump system.
      • Avoids reliance on the integrity of the old brickwork.
      • Reduces preparation time by eliminating the need for wall sandblasting.
    • An Aquadrain channel was installed around the perimeter at the floor-wall junction, an area prone to water ingress.
  3. Internal Wall Finishing:
    • The membrane was fixed using Oldroyd brick plugs, which also accepted battens via No.12 screws.
    • Plasterboard was then mounted on the battens to form the finished wall surfaces.
  4. New Installations:
    • Ceilings, lighting, sockets, and plumbing were installed to modern standards.

A humidistat-controlled extractor fan was added to regulate humidity and maintain a healthy indoor climate, compliant with BS8102 Grade 3.

The Outcome

The basement was successfully converted into a dry, habitable space suitable for its new functions: a playroom, guest bedroom, and wet room.

The project:

  • Maximised the available headroom through thoughtful excavation and stepped flooring.
  • Utilised an efficient, modern waterproofing system tailored for heritage buildings.
  • Was completed faster due to reduced surface preparation requirements.
  • Met environmental standards for habitable basements, ensuring comfort, durability, and value for the homeowner.

This case demonstrates how a sensitive and strategic approach can unlock the potential of heritage properties while preserving structural integrity and meeting contemporary living standards.